Troubleshooting: Workaround for switching procedure plans or adding tasks with billingTopic number: 1600440972212
When billing is configured and you need to switch procedure plans or add tasks after a technical charge was sent, you must restore the original acquisition task to ensure that subsequent acquisition tasks are billed correctly.
Issue
Original acquisition tasks are not being credited after an acquisition task cancellation and procedure plan switch or addition of new acquisition and follow-up tasks.
Details
- Complete the preparation task.
- Cancel the acquisition task.
A technical charge is sent.
- Then do one of the following:
- Switch the procedure plan and create another acquisition task (based on the new procedure plan).
- or
- Add acquisition and follow-up tasks.
No technical credit is given for the tasks performed as part of the original procedure plan.
Solution
- Restore the acquisition task.
This ensures that a technical credit is sent.
- Switch the procedure plan.
The restored acquisition task is canceled.
Preparation and acquisition tasks are created (based on the new procedure plan).
- Complete the preparation and acquisition task.
A technical charge is sent.
Required permissions:
- Can cancel acquisition task
- Can switch procedure plans